Responsibilities:
- Working closely with the Department Heads & I will be responsible for ensuring the control of Site and other site related technical & non-technical problems
- Proper utilization of manpower, equipment’s & Materials to achieve the given target
- Preparing a daily progress report & submitting to the department head
- Preparing the Bar Bending schedule as per the engineering drawings
- Attending the Progress Meeting with clients and Subcontractors.
- Dealing with client for Technical issues in the Engineering drawing & raising the technical queries.
- Raising the Material request for the required material as per the Engineering drawings
- Checking the daily work permits & renewing if expired.
- Distributing the daily work to the Site Supervisors as per there capacity and project priorities.
- Ensuring the availability of all materials before the work start.
- Calculating the required quantities of Rebar, Formwork, Anchor bolts, Insert plates etc.
- Maintaining the area clean with proper housekeeping.
- Inspecting the site daily with the QC of client to fulfill the quality requirement
- Inspecting the site daily with Safety of client to fulfill the safety requirement
- Advising the client supervisors & engineers for any revision required the given drawings.
Major Construction Work done:
- Construction of Waste Water Treatment Plant (WWT) in RRE Project.
- Construction of Heavy Substations, Blast Proof substations & Oil spill center building.
- Construction of Onshore clusters, Remote well areas, Water supply & water disposal well areas in Al Dabbiya phase III Project of ADCO / ADNOC.
- Excavation & Backfilling of HV & LV Cable Trenches.
- Construction of Precast Manholes, Catch basins, Electrical Duct banks, Concrete cable trenches & miscellaneous foundations.
- Construction of Heavy Water retaining Structures circular & rectangular (More than 7mtr height).
- Construction of Pipe culverts, Slab culverts, Pipe trenches, Cable trenches.
- Construction of Equipment foundations, Pipe Racks fdns, Sleeper fdns, Pipe support fdns.
- Leak tests for Heavy Water Retaining Structures.
- Constructions of Heavy duty & Light duty concrete paving.
- Water proof, Acid proof, Chemical proof Coatings of concrete structures.
- Construction of Slope Protection, Underground Ditches, Circular Tanks.
- Installation of Interlock, Kerb Stones, Tiles Etc.
- Concreting of Heavy Raft Foundations, Walls, Pile caps, Massive concrete elements and Pedestals
- Concrete Block work of Multi Storey Buildings in UAE & INDIA.
- Plastering, Painting & Finishing of the structure.
- High security fence work as per ADCO / ADNOC requirement in UAE.
- CFA (Continuous Flight Auger) Piling work done in PP5 Project.
- Asphalt Road works in PP5 Project 90,000 M2.
Details about Major project worked in UAE:
- Project: RRE#3 O&U Project, Ruwais Industrial Area, Abu Dhabi.
Designation: Civil Site Engineer
Scope: This is the Refinery Expansion Project Owned by Takreer. Under the Main Contractor Samsung Engineering, The duration of work is from Dec-2010 to June – 2011.
- Project: Carbon Black and Delayed Coker Project, Ruwais Industrial Area, Abu Dhabi.
Designation: Civil Site Engineer
Scope: This is the Refinery Expansion Project Owned by Takreer. Under the Main Contractor Samsung Engineering, The duration of work is from June-2011 to Dec – 2016.
- Project: ADCO Al Dabbiya Surface Facilities Phase III Project, Abu Dhabi
Designation: Civil Site Engineer
Scope: The Purpose of this Project mainly produced a H2SGAS by ADCO. Under the Main Contractor Tecnimont SPA, The duration of work is from Jan-2016 to Dec – 2018.
- Project: BOROUGE Polypropylene (PP5) Project Ruwais industrial Area, Abu Dhabi.
Designation: Civil Site Engineer
Scope: The Purpose of this Project is mainly to produce a Polymers (Polypropylene). The duration of work is from Jan-209 to till date.