Summary

Risk Engineer specializing in Power Generation with close to 15 years of rich experience across General Insurance with industry leaders like Chubb and AIG.

Expert in conducting high-impact technical surveys that protect plant revenue and provide critical advisory to underwriters for optimized risk selection.

A unique bridge between field-level engineering and insurance portfolio management, dedicated to elevating risk quality and operational excellence.

Thorough knowledge of risks associated with construction and operation of Power Plants.

Overview

25
25
years of professional experience

Work History

Senior Risk Engineer (Powergen)

Chubb Underwriting DIFC Ltd
05.2022 - Current
  • Enhanced portfolio quality by conducting comprehensive risk engineering surveys of power generation assets; provided critical technical advisories to underwriters that enabled data-driven pricing and informed terms/conditions for complex power plant risks
  • Optimized engineering processes by implementing innovative solutions and streamlining workflow.
  • Strengthened team technical competency by distilling key takeaways from the Siemens Energy Insurance Meeting into structured internal reports, aligning risk engineering strategies with current industry benchmarks
  • Mentored junior engineers, fostering professional development and technical expertise.

Senior Risk Engineer

AIG MEA Limited
08.2015 - 05.2022
  • Develop and manage client service plans for lead accounts.
  • Plan and conduct risk assessment surveys (physical and virtual) of Construction and Power Generation facilities for written and prospect accounts.
  • Conducted surveys for Power Generation facilities in Indian Subcontinent, Middle East, Africa, Russia, Turkey and South East Asia.
  • Led risk engineering surveys for Conventional power generation occupancies employing H , F and E Class Gas Turbine technology, thermal power plants operating on Super Critical and sub critical technology with installed capacities ranging upto 800 MW, 660 MW.
  • Led risk engineering surveys for renewable power generation facilities employing Concentrating Solar Power both Central Tower and Parabolic Trough technology, Photo Voltaic technology, Wind Turbines and Hydro Power.
  • Support underwriters with desktop reviews of Power Generation accounts.
  • Conduct account review for multilocation power plants.
  • Drive improvement in overall risk quality by suggesting loss control measures and risk improvement recommendations.
  • Produce comprehensive market reports to identify hazards, potential loss producing exposures and loss estimates.
  • Conducted training and loss experience sharing sessions with insureds.

Manager - Energy

TATA-AIG GENERAL INSURANCE COMPANY LTD
05.2011 - 08.2015


  • Support Underwriters as Loss Control Engineer specializing in Power Generation with risk assessment surveys and desktop reviews.

Manager - Pipeline Operations Centre

PIPELINE INFRASTRUCTURE LIMITED , formerly RELIANCE GTIL
07.2007 - 05.2011
  • Operated East West Pipeline - India's longest Natural gas underground pipeline, 1400 kms and 48 inch diameter across 10 compressor stations using 31 GE PGT25+ gas turbines driving Nuovo Pignone pipeline compressors in safe, reliable and efficient manner.
  • Managed O&M activities of pipeline, compressor stations, metering stations and mainline valve stations from Master Pipeline Control Centre at Navi Mumbai.
  • Established and updated gas custody transfer metering procedures and various Key Interface documents.
  • Assisted in commissioning activities of pipeline, compressor stations and metering skids.

Shift Engineer

STEAG ENCOTEC (INDIA) PVT LTD
05.2006 - 07.2007
  • Shift operations of 156.1 MW Combined Cycle Power Plant employing 2 Alstom GT8C2 gas turbines and one Alstom condensing steam turbine.

Field Engineer

UNITED PHOSPHORUS LIMITED UNIT 5
05.2005 - 05.2006

Field operations of 62 MW Combined Cycle Power Plant employing GE LM6000 PA Aero Derivative Gas Turbine and GE Condensing Steam turbine.


Executive – Mechanical Maintenance

United Phosphorus Ltd
09.2002 - 05.2005
  • Planned and conducted maintenance activities of 62 MW Combined Cycle Power Plant employing GE LM6000 PA Aero Derivative Gas Turbine and GE Condensing Steam turbine.
  • Conducted routine Borescope Inspections for gas turbines.
  • Assisted in Hot Gas Path replacement for GE LM6000 PA gas turbine.

Graduate Engineer Trainee

BARODA RAYON CORPORATION
11.2000 - 07.2001
  • Shift operations of 2 x 5 MW Thermal Power Plant employing Alstom Circulating Fluidized Bed Combustion Boilers, Stoker Fired Boilers and backpressure Steam Turbines.

Education

Post Graduate Diploma - Thermal Power Plant Engineering

National Power Training Institute
Nagpur, India
08.2002

B.E. - Mechanical Engineering

Government College of Engineering
Chandrapur, India
08.2000

Skills

  • Underwriting Decision Support, Risk Improvement Recommendations, Technical Due Diligence
  • Technical Risk Surveys, Loss Prevention, BI/PD Exposure
  • Well versed with applicable industry standards like NFPA and IEEE
  • Industry expertise - Operation & Maintenance of Combined Cycle Power Plant

Timeline

Senior Risk Engineer (Powergen)

Chubb Underwriting DIFC Ltd
05.2022 - Current

Senior Risk Engineer

AIG MEA Limited
08.2015 - 05.2022

Manager - Energy

TATA-AIG GENERAL INSURANCE COMPANY LTD
05.2011 - 08.2015

Manager - Pipeline Operations Centre

PIPELINE INFRASTRUCTURE LIMITED , formerly RELIANCE GTIL
07.2007 - 05.2011

Shift Engineer

STEAG ENCOTEC (INDIA) PVT LTD
05.2006 - 07.2007

Field Engineer

UNITED PHOSPHORUS LIMITED UNIT 5
05.2005 - 05.2006

Executive – Mechanical Maintenance

United Phosphorus Ltd
09.2002 - 05.2005

Graduate Engineer Trainee

BARODA RAYON CORPORATION
11.2000 - 07.2001

Post Graduate Diploma - Thermal Power Plant Engineering

National Power Training Institute

B.E. - Mechanical Engineering

Government College of Engineering
Dilipkumar Yadav