Summary
Overview
Work History
Education
Skills
Languages
Accomplishments
Timeline
Hi, I’m

JAFFER NIYASDEEN ABUBAKKAR

Dubai,UAE
JAFFER NIYASDEEN ABUBAKKAR

Summary

Accomplished Construction Manager with14 years of experience, recognized for assessing operational needs and developing solutions to save costs, improve revenues and drive customer satisfaction. Resourceful and well-organized with excellent leadership and team-building record.

Overview

15
years of professional experience
4
years of post-secondary education

Work History

ELSEWEDY POWER
DUBAI

Construction manager
08.2022 - Current

Job overview

  • Installation,Testing and Commissioning of 132kV Cable Shifting works for RACECORS S/S SEC-E Associated works
  • Circuit energized on 31-May-2019 and final reinstatement in progress.
  • Conducted critical pre-installation conferences with contractors, subcontractors and key stakeholders, negotiating best-possible project progression.

M/s EMIRATES ELECTRICAL LLC

Construction Manager
09.2018 - 08.2022

Job overview

  • EMIRATES ELECTRICAL ENGINEERING - DUBAI
  • Installation,Testing and Commissioning of 132kV Cable works for SLCONPRK 132/11kV Substations and Associated works., # :- 31131098
  • Installation,Testing and Commissioning of 132kV Cable works for KERANOLA 132/11kV Substations and Associated works.,
  • Led site teams to deliver timely, under-budget project completion.

Project V: PROJECT MANAGER
09.2018 - 08.2022

Job overview

  • ELSEWEDY ELECTRIC KSA
  • Construction of OHTL & UG for interconnection of Qatif-2 115/13.8KV S/S, Line#2 - Client - NG - EOA
  • Project Duration from Feb 2017 and Sep 2018
  • 115 kV double circuit, three phase, vertical configuration,approximately 8.60 kilometers long overhead Transmission line on COMPANY provided design of monopole steel structures using two (2)-795 kcmil "DRAKE", 2617 ACSR/AW conductor per phase
  • The entire overhead transmission line shall be shielded with two (2) Composite Optical Overhead Ground Wire (OPGW)
  • Designing, supplying and installing of 1x48 cores Non-metallic Underground Fiber Optic cables along with the New 115kV Power Cables Route
  • Design and construction of two (2) 115 kV Underground cable circuits
  • (3.80 kilometers long approximately)
  • And Performing associated Survey, Civil works including Trenching, backfilling, horizontal Directional Drilling across main road, and all other related WORKS.

SITE MANAGER
08.2015 - 01.2017

Job overview

  • ALFANAR CO KSA 380KV UG Cable installation Project in Makkah for SEC - Western Operating Region

CAPITAL LIGHT CO
Riyadh, Saudi Arabia

PROJECT ENGINEER
02.2009 - 07.2015

Job overview


  • Replacement of Existing 132kV DC OHTL from 8001 - 8003(A & B) with 132kV, 2000mm² U/G Cable in Riyadh for RAMPED/FAST/SAUDI ELECTRICITY COMPANY - Central Operation region
  • Project Duration from, Install two 132kV Underground circuits, each circuit consisting of 1×1C×20000mm², super clean -XLPE, Cu conductor, cable as per phase complete with all other accessories
  • Approximate route length of project is 12km
  • Design supply and installation of 1×96 cores Non Metallic Underground Fiber optic cable
  • Preparation of cable trench for direct buried cable installation
  • Construction of concrete encased duct bank and sand duct bank
  • Perform horizontal directional drilling in needed areas
  • Design and construction of Communication handholds, communication duct banks, installation of Hand hole accessories, duct and sub duct required for the installation of underground Fiber optic cable
  • Project II: PROJECT ENGINEER - CAPITAL LIGHT CO KSA
  • Interconnection between Saihat 115/13.8kV S/s#2 and As Sha'te 115/13.8kV S/s#2 for Saudi Electricity Company in Eastern operation region
  • Project completed and energized
  • Duration from

Education

ANNA UNIVERSITY
, Chennai, TamilNadu

Bachelor of Engineering from Electrical and Electronics Engineering
04.2004 - 05.2008

PMI

Successfully completed an intensive 35 hours training on Project Management work using PMI from Project Management Professional
2002

Skills


  • Exemplary communication
  • Risk mitigation and control
  • Construction documentation management
  • Labour resource allocation
  • Subcontractor management
  • Excellent customer relations
  • Permit approval process management

Languages

English
Fluent
Tamil
Native
Hindi
Advanced
Arabic
Intermediate

Accomplishments

  • Supervised team responsible for executing well on projects, leading to 8% increased revenue.
  • Collaborated with team of 6 in development of 132KV CABLE in Asphalted Road.

Timeline

Construction manager

ELSEWEDY POWER
08.2022 - Current

Construction Manager

M/s EMIRATES ELECTRICAL LLC
09.2018 - 08.2022

Project V: PROJECT MANAGER

09.2018 - 08.2022

SITE MANAGER

08.2015 - 01.2017

PROJECT ENGINEER

CAPITAL LIGHT CO
02.2009 - 07.2015

ANNA UNIVERSITY

Bachelor of Engineering from Electrical and Electronics Engineering
04.2004 - 05.2008

PMI

Successfully completed an intensive 35 hours training on Project Management work using PMI from Project Management Professional
JAFFER NIYASDEEN ABUBAKKAR