GASCO LPG Expansion Project, Riyadh, Kingdom Of Saudi Arabia
Scope of Work: Transport and Installation of 9 unit of Bullets tanks (L63m*W9.5*H11.7m- 856 MT) from Vendor Facility to Project site around 490 kms
Achievements:
- Lead the FEED of the project along with the project owner, studied and ensured the transport was feasible with the dimensions of the bullets
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 20 including engineers, operational staff and technicians
- Negotiated contracts with sub-contractors
- Successfully secured the phase 2 of the project during the execution of phase 1 of the project
VESTAS Dumah Al Jandal 400MW Windfarm Project, Kingdom of Saudi Arabia
Scope of Work: Transport of 20 sets of V150 WTG components from POD to the project site around 850kms
Achievements:
- Lead the 1st ever wind farm project in the kingdom
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 37 including engineers, operational staff and technicians
- Completed the project successfully and with zero incidents
Petro Rabigh Turnaround 2020, Kingdom of Saudi Arabia
Scope of Work: Replacement of 10 units of condensers by elevated jacking and skidding during the turnaround and transport of all heavy lift equipment for the turnaround from laydown area to foundations
Achievements:
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 36 including engineers, operational staff and technicians during the outbreak of the COVID-19 and was able to complete the project safely and on schedule
Clean Fuels Project, Saudi Aramco Rastanura Refinery, Kingdom of Saudi Arabia
Scope of Work: Transport of 34 units of Heavy Lift Equipment
Achievements:
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 21 including engineers, operational staff and technicians
- Completed the project successfully and with zero incidents
Aluminum Bahrain Potline 6 Project, Kingdom of Bahrain
Scope of Work: Transport and Installation of Various Heavy Lift Equipment- Stack Sections, Panels Sections, Overhead Cranes, Filter Sections
Achievements:
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead the engineering team to design a bespoke solution for the transport of the panel sections to save time and cost for the client
- Setup the branch in the kingdom
- Oversee the financial and operational management of the branch during the project tenure
- Negotiated contracts with sub-contractors
- Lead a project team of 12 including engineers, operational staff and technicians
- Completed the project successfully and with zero incidents
- Successfully negotiated additional scope of work of USD 0.3 million
- Solved contractual disputes of USD 0.1 million
Saudi Aramco Ethane Deep Recovery Facility Project, Uthmaniyah Gas Plant, Kingdom of Saudi Arabia
Scope of Work: Transportation of 92 Heavy Lift equipment including the De-Methaniser Column (L76M*W8m*H9M-1156MT) from Various port and fabricators yard to the project site
Achievements:
- Secured the business based on the technical and commercial offer submitted and negotiated the contract terms and conditions
- Lead a project team of 24 including engineers, operational staff and technicians
Other Projects Executed
- Saudi Aramco Abu Ali Gas Plant Substation Expansion Project – Transport & Installation of Power Transformers
- Ma’aden Phosphate Company, Ras Al Khair- Transport of 56 Heavy Lift Equipment from Various locations in Saudi Arabia to the site
- Saudi Aramco Shaybah GOSP-4 Power Plant Expansion Project- Transport & Installation of all Heavy Lift equipment’s (Generators, Turbines and Transformers) at site
- Saudi Electricity Company Qassim BSP 380kV Substation- Transport & Installation 10 units of Power Transformers
- Saudi Electricity Company Al Kharj BSP 380kV Substation- Transport & Installation of Power Transformers
- Riyadh Metro Project- Transport of several Heavy Lift equipment (TBM’s, Bridge Sections, Precast Sections, Precast Forms, Metro Rail Cars) from various locations across Kingdom
- Saudi Electricity Company CCG&SP Project- Transport & Installation of Power Transformers
- Saudi Electricity Company- Qassim Power Plant Expansion Project – Transport of HRSG modules to the project site
- LUBEREF Refinery Expansion Project- Transport of Heavy Lift equipment from various fabricator’s yard to site
- Jizan Refinery and Terminal Project (Power Block)- Transport of various Equipment to final foundations of erection
- Jizan Integrated Gasification Project- Transport of 72 Heavy Lift Equipment from Various fabricators yard and Ports in Saudi Arabia to Site
- Jizan Air Separation Unit- Direct Receiving & Transportation of Heavy Lift Equipment from Jizan Jetty to Site
- Saudi Electricity Company Mah’d Al Dhab BSP 380kV Substation- Transport & Installation of Power Transformers
- Saudi Aramco Fadhili Gas Program- Transport of Heavy Lift Equipment from Fabricators Yard to Project Site
- Saudi Aramco Fadhili Gas Program- Transport & Offloading of Air Coolers at Site
- Saudi Aramco Khurais Facilities Expansion Project- Transport of Heavy Lift Equipment for the Power Block Section from Port to Project Site
- SWCC Yanbu Phase 3 Expansion Power Plant Substation – Transport & Installation of Power Transformers at site
- Saudi Electricity Company Riyadh Airport BSP 380kV Substation- Transportation & Installation of Power Transformers
- Saudi Aramco Rastanura Refinery- Additional Hydrotreating Unit- Logistics and Equipment Lifting Feasibility Study
- South Ghawar Debottlenecking- Logistics and Equipment Lifting Feasibility Study
- North Ghawar Facilities Expansion Project- Logistics and Equipment Lifting Feasibility Study