Seasoned professional with 20 years of experience in delivering diverse projects on time and within budget. Expertise in supervising technical teams to ensure compliance with specifications and project goals. Proven track record of maintaining strong client relationships while managing complex assignments. Committed to achieving high-quality results through effective collaboration and problem-solving skills.
Projects Undertaken:
Responsibilities:
Projects Undertaken:
My Home Ankura Project – Located in Tellapur, Hyderabad, the development consists of 603 premium villas spread across 75 acres. In my role as AGM, I was responsible for constructing 72 villas, along with completing the clubhouse, swimming pool, and park. Successfully delivered 50 out of the 72 villas, in addition to the clubhouse and park.
Projects Undertaken: Construction of Hotel Apartments building (2B+G+M+6) in Rawdat Al Khail
Responsibilities:
Projects Undertaken: : Lulu Hypermarket, Rashidiya, Dubai, UAE. Consultant: ADS Architectural Consultants, Dubai, UAE. Client: LULU, AL Naboodah Real Estate Investment LLC, UAE
:Projects Undertaken: Muscat Bay (Saraya Bandar Jissah) – Residential development @ Zone 3, Zaha, Qantab, Muscat, Oman (42 villas & 21 five storey buildings) Consultant: KEO International, Client: Muscat Bay (Saraya Bandar Jissah)
Projects Undertaken: Public Authority Of Civil Aviation Headquarters Building (MC4a,PACA), Seeb, Muscat, Consultant: HILL International, Client: Public Authority of Civil Aviation (PACA)
Projects Undertaken: Abu Dhabi Future School Project, Al Ain, UAE, Consultant: KEO International, Client: Abu Dhabi Education Council, Project Manager: Musanada, Hill International
Projects Undertaken:
Project 1: Construction of two residential buildings, (2B+G+6) for ADNIC, Khor Al Raha, Abu Dhabi, Consultant: Dar Al Handasah, Project Manager: Turner Construction
Project 2: Al Bateen Secondary School, Al Dar, Abu Dhabi, Consultant: Dewan Architects, Client: Al Dar
Projects Undertaken:
Project 1: Proposed Expansion of Indian School, Kingdom of Bahrain Consultant: Arif Sadiq Design Consultants, Client: Indian School
Role: Project Engineer In charge for the construction of Indian school for all structural and finishing Works. Involved in all construction activities from starting to hand over. Studying the drawings, specifications and confirming the compliance with project requirements, Responsible for mobilization of men, machinery, material and necessary resources. Site Coordination and follow up of daily project construction activities
Project 2. Replacing the main gas line pedestals at Riffa Power Station Client: Ministry of Electricity and Water, Kingdom of Bahrain. Project 3. Civil Works for ILS System (instrument landing system) at M26 for Bahrain Defense Force, Kingdom of Bahrain.
Project 4. Maintenance works at Sitra power station, Riffa power station, Hidd power station.
Project 5. Construction of Shops for SEEF MALL (Interior works) Project 6. Construction of labour accommodation& shops building at Tubli
Project 7. Major modifications at Gulf Air Head Quarters, Kingdom of Bahrain (interior Works)
Project 8. Maintenance works at LPP, Al Fateh building, Ministry of Health (interior Works)
Project 9. Construction of Security Room for Ministry of Electricity & Water
Project 10. Bahrain Defense Force Maintenance Works
Projects Undertaken:
Project 1. Construction of nine storey Building "AVON DALE"
Involved in Construction of Building from 6th floor Structural works up to finishing works of 21 flats, out of 36 flats
Project 2. Construction of eight storey Building" ASTER PLACE".
Involved in Construction of Building at the level of PILE Foundation stage.
I hereby certify that all the above-mentioned information are true and correct to the best of my knowledge and ability. I feel that your organization offers greater ambit for my abilities and would sincerely love to enjoy the challenges of new environment and expect a positive contribution in the position given by you.
PMP, PMI-RMP